46.1     ACO Evans submitted the Corporate Services programme, projects to date and performance against Corporate Services performance indicators and associated targets for the third quarter of 2017/18.

 

46.2     The Asset Tracking System was currently deferred pending a further report to the Service’s Corporate Management Team.

 

46.3     The Website Procurement and Development project was making good progress and Members would shortly be sent a link to participate in user testing. The work undertaken by AC D Cook and his team on this project was recognised.

 

46.4     The Protection Replacement Management Information System remained on Amber as there were still ICT training issues to resolve. The Prevention part of the Information System project was rated as green.

 

46.5     The non-sickness absence synchronisation module of iTrent was rated red as issues had arisen due to a lack of capacity and the complexity of the integration. This would continue to be monitored. The people/person synchronisation was also rated red but would be completed by the end of the week.

 

46.6     The unified communications project was rated as amber as there had been some slippage arising from configuration issues. The provider had offered an on-site resource to drive through the changes required and the rate of progress had increased as a result.

 

46.7     The community defibrillator project was complete and would be closed down as a reportable project, as would the Desktop Refresh (VDI). A small group of users had not yet been migrated across but this would take place under the new VDI Upgrade project which would continue to be reported to the Group.

 

46.8     It was requested that a link to iTrent be recirculated to Members to enable them to access their P60s.

 

46.9     ACO Evans then reported on the performance indicators as at the end of the third quarter of 2017/18. All ICT and Fleet and Workshops indicators were reporting as green, with the exception of WS1a (Grade A defect response time (within 1 hour)), which had not recovered from poor first quarter performance caused by a vacancy in the workshop. The post had now been successfully recruited to and performance was meeting target levels for the quarter, but as performance was cumulative, it was still reporting as amber and was likely to do so at year end.

 

46.10   Mr G Chambers, the Head of Finance and Treasurer, reported on the indicators, two of which had not achieved target levels. FNP5 (percentage of uncontested invoices paid within 30 days) had missed its target by 1%. The Finance Team regularly liaised with departments to resolve issues with the late authorisation of invoices and/or raising of purchase orders which delayed payment of invoices.

 

46.11   FNP6 (percentage of outstanding debt over 90 days old) was red as a result of underperformance in quarter 1 arising from a vacancy. A table should have been included in the exception report to illustrate that performance against the indicator continued to improve, with performance of 18.6% in quarter 1, 0.73% in quarter 2 and 1.49% in quarter 3. Changes were being proposed to the way this indicator was reported to give a more accurate reflection of quarterly performance.

 

46.12   Members asked that a link be sent to them to enable to access their P60s via iTrent.