Agenda item

To consider a report

 

Minutes:

ACO Evans submitted the Corporate Services programme, projects to date and performance against Corporate Services performance indicators and associated targets for the second quarter of 2017/18.

 

The Asset Management System project had been postponed due to limited capacity to support the development of the project. The project would be reconsidered in Summer 2018 and would be removed from the programme until that time. The paper based system currently in use was robust and this system would continue until an electronic system was developed and implemented.

The Website Procurement and Development project was rated as green as the development of a new website was being progressed and it was anticipated that the new website would be launched by March 2018.

 

The Fire Safety Management Information System project was currently reporting as amber due to the limited capacity within the ICT Team.

 

The Workbench Development – Sickness Absence Application had been completed and would be removed from the programme report. This had streamlined the sickness reporting process.

 

The Workbench Development – Non-Sickness Absence Application had not yet been completed and was reporting as red as the completion date of September 2017 had been missed. It was expected that this would now be completed by mid-January 2018.

 

The iTrent/MIS Synchronisation project was reporting as red as the completion date of September 2017 had been missed and would be completed by mid-March 2018.

 

The Training Centre Administration workstream was reporting as amber and a further update would be provided at the next meeting of the Group.

 

The HR/Payroll System and Services was reporting as amber although the system has been implemented successfully.   The project had been audited by the external auditors and was being rated as amber to enable the high level of monitoring to continue by the project board.

 

The Retained Recruitment, Telephony Systems Replacement and the Community Defibrillator projects were green.

 

The Desktop Refresh project was substantially complete with only a small number of complex cases awaiting migration.

 

ACO Evans then reported on the second quarter performance information. All ICT indicators and all but one workshop indicator had met or exceeded target levels.

 

WS1a (Grade A defect response time (within 1 hour)) was reporting as amber for the quarter. AC D Cook advised that there had been a technician vacancy and this had affected the rota group. This post had now been successfully recruited to, with the applicant completing the training required to join the rota group. As such, performance against the indicator should improve in future quarters.

 

FNP5 (percentage of uncontested invoices paid within 30 days) was also reporting as amber, as it had missed its target of 96% by 2%. The processing of invoices had been delayed in certain departments due to changes in staffing, leave and sickness. The Finance Team was liaising with the departments concerned to ensure that performance against this indicator improved.

 

FNP6 (percentage of debt over 90 days old) had missed its target of 2.55% and was 9.66% at the end of the reporting period. There had been vacancies in the Finance Team during the period and following the successful recruitment to the post, the total debt outstanding as at 30 September 2017 was £37,000, with only £271.20, or 0.73%, over 90 days old.

 

The Chair suggested that the wording of FNP6 be revisited at the Group’s target setting meeting on 13 March 2018 to ensure that debt over 90 days was being measured against the percentage of the total debt that had been raised.

 

RESOLVED:

1.         That the progress made on Corporate Services Programmes and Performance be acknowledged.

2.         That the Group consider amending the wording of FNP6 (percentage of debt over 90 days old) at its target setting meeting in March 2018.

 

Supporting documents: